[Blocker] Bay-3 exhaust hookup delay blocks Commissioning start #1

@QuantuMaster007

Description

@QuantuMaster007

Gate impacted: Install / Comm
Severity: Sev-2
Owner: Facilities Eng

What is blocked?

  • Exhaust hookup for Bay-3 not complete → tool cannot enter Commissioning.
  • Impacts commissioning window and downstream SAT.

Evidence / data references

  • Check readiness rollup: data/processed/readiness_rollup.csv
  • Blocked tasks: data/raw/facility_readiness_tasks.csv

Mitigation / next steps

  • Temporary ducting workaround + EHS signoff (timeboxed)
  • Escalate hookup schedule; confirm crew availability

Exit criteria

  • Exhaust hookup complete OR approved workaround in place
  • Update readiness + regenerate evidence outputs