Gate impacted: Install / Comm
Severity: Sev-2
Owner: Facilities Eng
What is blocked?
- Exhaust hookup for Bay-3 not complete → tool cannot enter Commissioning.
- Impacts commissioning window and downstream SAT.
Evidence / data references
- Check readiness rollup: data/processed/readiness_rollup.csv
- Blocked tasks: data/raw/facility_readiness_tasks.csv
Mitigation / next steps
- Temporary ducting workaround + EHS signoff (timeboxed)
- Escalate hookup schedule; confirm crew availability
Exit criteria
- Exhaust hookup complete OR approved workaround in place
- Update readiness + regenerate evidence outputs