Report Author: Mathew Jackson |

Author ID : 2152277 |

Author Team : Death Star |

Class Section: 801


###User stories to work with:

Write a Review of team: 3 days - 40

Select a game style: 2 days - 10

Set user preferences: 4 days - 30

Create a new team: 5 days - 10

Delete a lineup: 3 days - 20

Delete a player: 3 days - 20

Favorite teams save feature: 3 days - 50

Live feed fantasy tips: 4 days - 50

Search community teams: 3 days - 30

###Total days: 30 days of work

##Priorities to work with: ####20x, 30x, 40x, 10x, 30x, 50x, 20x, 10x, 50x

#Plan A: ###(30 day iteration, 2 developers, 0.7 velocity) ###20, 30, 40, 10, 30, 50, 20, 10, 50

###With velocity: 43 days (rounded up) ###2 people x 30 day iteration x 0.7 = 42 days total to finish ###One iteration will be <= 30 days ###Second iteration will be 12 days

##Organized ###Select game style = 2 days, priority of 10 #-velocity: 3 days ###Create a new Team = 5 days, priority of 10 #-velocity: 7 days ###Delete a player = 3 days, priority 20 #-velocity: 4 days ###Delete a lineup = 3 days, priority 20 #-velocity: 4 days ###Set User Preferences = 4 days, priority 30 #-velocity: 6 days ###Search Community teams = 3 days, priority 30 #-velocity: 4 days ###Write review of a team = 3 days, priority 40 #-velocity: 4 days ###Favorite team save feature = 3 days, priority 50 #-velocity: 4 days

###Velocity days: 49 days

##ITERATION 1 with velocity taken into account: 27 days ###Select game style = 3 days, priority of 10 ###Create a new Team = 7 days days, priority of 10 ###Delete a player = 4 days, priority 20 ###Delete a lineup = 4 days, priority 20 ###Set User Preferences = 6 days, priority 30

####ITERATION 2 with velocity taken into account: 12 days ###Search Community teams = 4 days, priority 30 ###Write review of a team = 4 days, priority 40 ###Favorite team save feature = 4 days, priority 50

#Plan B: ###(User added 2 additional user stories at priority 10) - assume you were at the ###end of the first iteration when these were introduced. ###For the 2 new stories: 1 is a feature, the other is an emergency: ###20, 30, 40, 10, 30, 50, 20, 10, 50, 10(new), 10(emergency)

##NOW 10 user stories:

##Organized ###Emergency user story = 3 days, priority 10 -velocity: 4 days ###New feature user story = 3 days, priority 10 -velocity: 4 days ###Select game style = 2 days, priority of 10 -velocity: 3 days ###Create a new Team = 5 days, priority of 10 -velocity: 7 days ###Delete a player = 3 days, priority 20 -velocity: 4 days ###Delete a lineup = 3 days, priority 20 -velocity: 4 days ###Set User Preferences = 4 days, priority 30 -velocity: 6 days ###Search Community teams = 3 days, priority 30 -velocity: 4 days ###Write review of a team = 3 days, priority 40 -velocity: 4 days ###Favorite team save feature = 3 days, priority 50 -velocity: 4 days

###With velocity: 43 days (rounded up) ###2 people x 30 day iteration x 0.7 = 42 days total to finish ###One iteration will be 29 days ###Second iteration will be 14 days

##NEW ITERATION 1 with velocity taken into account and emergency story: NOW: 29 days ###Select game style = 3 days, priority 10 ###Create a new Team = 7 days days, priority 10 ###Delete a player = 4 days, priority 20 ###Delete a lineup = 4 days, priority 20 ###EMERGENCY Story = 4 days, priority 10 ###NEW USER FEATURE = 3 days, priority 10 ###Search Community teams = 4 days, priority 30

##NEW ITERATION 2 with velocity taken into account and extra feature: NOW 14 days ###Set User Preferences = 6 days, priority 30 ###Write review of a team = 4 days, priority 40 ###Favorite team save feature = 4 days, priority 50

##Reality scenario ##ITERATION 1 with velocity taken into account: 26 days ###Select game style = 3 days, priority of 10 - completed ###Create a new Team = 7 days days, priority of 10 - completed ###Delete a player = 4 days, priority 20 - completed ###EMERGENCY STORY = 4 days. priority 10 -- now working on ###New user story = 4 days, priority 10 ###Delete a lineup = 4 days, priority 20

##ITERATION 2 with velocity taken into account: 18 days ###Set User Preferences = 6 days, priority 30 ###Search Community teams = 4 days, priority 30 ###Write review of a team = 4 days, priority 40 ###Favorite team save feature = 4 days, priority 50

What happened:

Because of the new stories that were added while at the end of Iteration 1, We would

have to push a 6 day user story to the next iteration, making iteration shorter in the long run,

but now iteration 2 has 18 days. Note that the NEW FEATURE user story is immediatly after emergency.


##Plan C: ###(A user-story with a non-trivial estimate is taking 2x longer) ###20, 30, 40, 10, 30, 50, 20, 10, 50 ###With velocity: 43 days (rounded up) ##2 people x 30 day iteration x 0.7 = 42 days total to finish

##Organized ###Select game style = 2 days, priority 10 #-velocity: 3 days ###Create a new Team = 5 days, priority 10 #-velocity: 7 days ###Delete a player = 3 days, priority 20 #-velocity: 4 days ###Delete a lineup = 3 days, priority 20 #-velocity: 4 days ###Set User Preferences = 8 days, priority 30 #-velocity: 11 days ###Search Community teams = 3 days, priority 30 #-velocity: 4 days ###Write review of a team = 3 days, priority 40 #-velocity: 4 days ###Favorite team save feature = 3 days, priority 50 #-velocity: 4 days

###Velocity days: 49 days

##NEW ITERATION 1 with velocity taken into account, 2x longer story: 29 days ###Select game style = 3 days, priority of 10 ###Create a new Team = 7 days days, priority of 10 ###Delete a player = 4 days, priority 20 ###Delete a lineup = 4 days, priority 20 ###Set User Preferences = 11 days, priority 30

##NEW ITERATION 2 with velocity taken into account, 2x longer story: 12 days ###Search Community teams = 4 days, priority 30 ###Write review of a team = 4 days, priority 40 ###Favorite team save feature = 4 days, priority 50

####How to adjust for this scenario: Luckily, iteration 1 had enough ####room to accomodate the larger time period for the non-trivial user story.

##Reality scenario ##ITERATION 1 with velocity taken into account and emergency story: NOW: 24 days ###Select game style = 3 days, priority of 10 - completed ###Create a new Team = 7 days days, priority of 10 - completed ###Delete a player = 4 days, priority 20 - completed ###Delete a lineup = 4 days, priority 20 - completed ###EMERGENCY Story = 3 days, priority 10 - completed ###NEW USER FEATURE = 3 days, priority 10 - in progress

##ITERATION 2 with velocity taken into account and extra feature: NOW 23 days ###Set User Preferences = 11 days, priority 30 ###Search Community teams = 4 days, priority 30 ###Write review of a team = 4 days, priority 40 ###Favorite team save feature = 4 days, priority 50

###In the reality scenario, we were sprung with a problem with our last user story taking ###longer, therefore we needed to post pone the 2x longer story to the next iteration, ###and swap out a smaller time estimated storyfrom iteration 2 for the last part of iteration ###1. This made the total of iteration one into 24 total work days, and increased iteration 2 ###to 23 days of work.

##Plan D: ###(The other developer is taken for another project)(Lone wolf style) ###-At the start of the last iteration of your current plan ###1 x 30 x 0.7 = 21 days of actual work solo with 0.7 velocity in 30 day ###However, 8 days remain of actual work, with 11 days to spare

##NEW ITERATION 1 with velocity taken into account: 18 days ###Select game style = 3 days, priority of 10 ###Create a new Team = 7 days days, priority of 10 ###Delete a player = 4 days, priority 20 ###Delete a lineup = 4 days, priority 20

##NEW ITERATION 2 with velocity taken into account: 18 days ###Search Community teams = 4 days, priority 30 ###Set User Preferences = 6 days, priority 30 ###Write review of a team = 4 days, priority 40 ###Favorite team save feature = 4 days, priority 50

##Reality scenario ##ITERATION 2 with velocity taken into account and extra feature and 1 developer: 19 days ###Set User Preferences = 11 days, priority 30 ###Search Community teams = 4 days, priority 30 ###Write review of a team = 4 days, priority 40

##ITERATION 3 with velocity taken into account and extra feature and 1 developer: 4 days ###Favorite team save feature = 4 days, priority 50

####What happened: At the beggining of iteration 2, a developer was switched from project, thus having ####to re-evaluate the velocity with work days and re adjust an iteration plan. This time a single worker ####will get 21 days of work done in a 30 day iteration at a velocity of 70%. This caused a change in iteration ####2 that had to push "Favorite team save feature" to a brand new iteration to guarentee that user stories ####will all be completed within the given iteration.